Breakdown of the Costs for the Room Construction

Here is the breakdown of the room construction materials and labor construction material:


1 truck of sand $ 171.98
1 truck of small rocks $ 127.47
35 bags of cement $ 388.46
47 rods $ 157.69
15 roof sheets $ 192.31
4 kilos of black wire $ 6.59
8 boxes of small nails $ 7.14
40 roof hooks $ 4.95
550 bricks $ 403.85
IVA tax: $ 168.68
Subtotal Construction material: $ 1,629.12
Labor hand: $ 1,060.44
Subtotal construction material and labor hand: $ 2,689.56
Plus 10% (provisional fund) $ 269.00
Total: $ 2,958.56